PMC MEETING POINTS-30-11-2018
My dear Sir/Madam,
Warmth Greetings to you all
The first PMC Meeting in respect of OUR CHENNAI Ph-3 was
attended by me as well as other co-members on 30.11.2018. The meeting was chaired & inaugurated by Sh.Bhupinder Singh, CEO,ND, by a welcoming
note.
Apart from various points discussed
like quality materials, plumbing of water lines etc. by other members, I
focused and insisted mainly about two points :
Ø Suitably appealed the CEO to make all
efforts to hand over the DUs, by MID of 2020, as it has been always been a view
of mine shared among some of our Allottee friends.
Ø Made a suggestive request to reduce
the total cost* of each flat (ie.to refund the money after final payment) which
would benefit all our members since their committed financial burden would be
lessened to that extent. (*Actually the CEO, in his initial briefing he told
about various projects across the nations and quoted that CGEWHO actually
refunded some money in Bhuvaneswar Project.
This statement of him comforted me to put forth such an Important
request, though I had the same idea in me.)
Ø I asked for the Type wise Vacancy
Position: for which it was replied vague
or in a generalized way- “All are having waiting lists “
Ø To a query from one of our members about
the possible demand of next installment, it was replied that it may take
approximately say 4 to 6 months presumably from 30th Nov 2018.
Ø As per them, the overall progress of
the Project is not ahead of the Schedule. May be to be still speeded up. They
have the plan to increase the number of workers to different Blocks, it was
stated.
Ø
And ofcourse for the information of our esteemed members, a
joyful news is that they have done a model flat of outlined nature (i.e. done
the partition walls alone). One could feel as to how the flat would be
spacious.
The meeting went for little more than an hour
and wound up.
Tentative date about the
next PMC meeting was NOT mentioned.
-R MOHAN
(Below I am also posting some of the
Pictures taken on that day in the meeting as
well as at the site.)
Thanks for your update sir. Next time post some pics of model flat if possible. Dr Manicavassou New Delhi
ReplyDeleteSure Dr Vasoou.Tku very much for ur support.
DeleteWork has come to a halt. Is it true?
ReplyDeleteYes. Its true. Hble High Court has statyed the work bec of the WP preferred by Phase-2 Owners Assn. The outcome will be known in this month middle. We have to wait.
Delete-R MOHAN
Sir, What is this WP preferred by Phase-2 Owners Assn mean ?
DeleteAny update in the court case?
ReplyDeleteYes Mr.Murugaiyan. Till today there is no outcome about it. I hope you are from New Delhi.
DeleteWe are expecting the judgement at any day. Once it is coming out, you may please watch at my whatsapp statuse on my mobile 9486100452
regards
-R MOHAN
Thanks for the prompt response.
ReplyDeleteAppreciate that Mr. Mohan is giving the updates. Work is halted since Dec. No information available on the Cgewho website. It seems that Cgewho is not taking earnest efforts to vacate the stay order. The delay in project will impact in cost escalation. It is request that PMC may initiate for an immediate meeting to resolve the issue. Also individual representation by allottees may be thought of for bringing the attention of Cgewho officials for active involvement in vacating stay. Hope PMC members will take initiative on above and share us the feedback. Regards Anu bhaskaran.
ReplyDeleteLeant from Mr. Mohan that the stay got vacated. Pl inform whether construction resumed.
ReplyDelete